10 Finish assignment

To finish the installation, take the following final actions before leaving the site.

Figure 10.1. Closing of the Connection Compartment.

1) Slide on the Connection Compartment lid (see figure 10.1). 2) Lock it using a padlock. 3) Make sure the genset is set to Auto mode on the genset control panel. 4) Make sure the battery cabinet door is closed.

Figure 10.2. Green LED indicator on Connection Compartment.

5) Make sure the green LED on the Connection Compartment comes on (see figure 10.2). 6) Clean up the working area.

http://www.esitepowersystems.com

Copyright © 2021 eSite Power Systems AB