9 Finish assignment

To finish the installation, take the following final actions before leaving the site.

Figure 9.1. Grounding the Connection Compartment lid.

1) Ground the Connection Compartment lid. Attach the cable to ground the Connection Compartment lid (see figure 9.1). The cable is prewired to the Connection Compartment.

Figure 9.2. Closing of the Connection Compartment lid.

2) Slide on the Connection Compartment lid. Attach the lid with the screw on the bottom of the Connection Compartment (see figure 9.2). 3) Make sure the genset is set to Auto mode on the genset control panel. 4) Make sure the battery cabinet door is closed.

Figure 9.3. Green LED indicator on Connection Compartment.

5) Make sure the green LED on the Connection Compartment comes on (see figure 9.3). 6) Clean up the working area.

http://www.esitepowersystems.com

Copyright © 2021 eSite Power Systems AB

Last updated

Was this helpful?